Pages

July 13, 2026

DO YOU HAVE BACK UP POWER TO SAFETY CRITICAL EQUIPMENT?

A transformer caught on fire at 7:45 pm on a production building’s basement floor at a pharmaceutical plant. The building’s electrical power was cut, causing shutdown of the reactors’ stirring and cooling mechanisms. An exothermic reaction that was taking place at the time became uncontrollable. The reactor’s rupture disc, calibrated at 4 bar, broke, and the explosion vent opened to protect the structural integrity of the reactor. A quantity of the reaction mix at 70°C, composed of several hazardous products, projected onto one employee and six fire-fighters in the vicinity and formed a 60-m² puddle on the floor. 

The plant operator activated the internal emergency plan and the facility was evacuated. The safety report conducted on-site had not identified any comparable scenario. No backup source had been allocated to ensure the continued operations of critical equipment. Activities assigned to the damaged building and associated solvent storage zone were suspended until the safety systems (fire detection control, both post and automatic extinction) were once again operational. A diagnostic assessment of all site electrical installations was performed, along with a study, on the backup power supply for critical equipment, dedicated to exothermic reactions, i.e.: cooling, stirring, temperature and pressure probes.

Source:Aria database

July 8, 2026

LIGHTNING STRIKE DAMAGES CARD

A thunderstorm struck in the vicinity of a flammable liquid storage facility protected by an early streamer emission lightning rod. The indirect effects of the lightning damaged one of the 4 computer interface cards. This particular card had interfaced with the bus network responsible for relaying high-level safety alarms from the storage tanks. The facility operator detected the malfunction via the depot supervisor, who had indicated the communication breakdown. The operator did not possess a backup card and was unable to perform a quick replacement. He decided to inform the entire operating staff and requested extra vigilance when monitoring the performance sheets. Operations continued in this manner for 5 days before the interface card could actually be replaced. The damaged card had not been protected against indirect lightning effects. Following this accident, the operator kept on hand an additional card as a backup and implemented the recommendations issued in the study on indirect lightning effects conducted in April 2006. These recommendations focused on the protection, mainly by lightning rod, of the supervisor’s computer, alarm relay units, sensors, utility rooms, fire pumps serving 3 depots, and the electric generating sets for 2 sites.

 Source: Aria ACCIDENT ANALYSIS OF INDUSTRIAL AUTOMATION

July 3, 2026

AMMONIA RELEASE DUE TO LACK OF DIAGNOSING THE PROBLEM

 On a tubular exchanger, a disc broke over ¼ of its cross-section at 4:50 am during a pressure surge in the liquid ammonia (NH3 ) circuit connecting NH3 storage cells to a urea workshop operating under stable conditions. NH3 was partially led to a 100-m high degassing stack. Given stable weather conditions, a foul-smelling cloud drifted towards the city. The release occurred unbeknownst to control room operators, who had incorrectly interpreted several alarms that had tripped. Once the diagnosis rendered, the device was isolated at 6:25 am. The plant operator only became aware of the severity of the event at 8 am; two and a half hours were then needed to fully determine the origin and likely causes. The 10 tonnes of NH3 release was due to a succession of physical, organisational and human malfunctions: - Lack of anomaly detection and automatic safety systems: information made available to control room operators was inadequate; - Poor diagnosis / decision-making process lacking adequate verifications despite several precursors; - Incomplete safety recommendations, insufficient monitoring procedures and inspection plans. This poor diagnosis would explain the delay required to isolate the deficient circuit and the potential impact of this release. Long periods elapsed between the onset of the accident, the alarm and activation of the internal emergency plan, source identification, causes and circumstances of the discharge, and then a definitive quantification.

Source: Aria ACCIDENT ANALYSIS OF INDUSTRIAL AUTOMATION

June 27, 2026

DOMINO EFFECTS DUE TO POWER NON AVAILABILITY NOT CONSIDERED DURING DESIGN

 In a Seveso chemical plant, a fire broke out at 12:59 pm in a substation supplying a hydrazine hydrate unit. An electrical fault on a cooling water pump caused a generalised short circuit on an electrical tower. The fire alarm was triggered at 1.00 pm. The fire spread to the other towers of the panel through the subfloor. The 400 V circuit breaker located upstream was blocked and did not function. The fault current passed through the 13,000 / 400 V transformer, there was overpressure and an oil leak followed by a primary side homopolar fault causing the 13 kV circuit breaker to trip. The absence of voltage caused the diesel generator set to stop but the switchover to the emergency system failed as the automatism was damaged by the fire. The smoke spread to the UPS room whose door remained opened. The UPS stopped when a high temperature (> 40 °C) was reached causing the loss of control and command on the process. The component switched over to safety mode. Due to the lack of power supply, the cooling system, agitation and the internal and external emergency plan siren were no longer functional. Since the ongoing reaction was exothermic, the reactor temperature and pressure increased. Several measures are taken such as designing an emergency cooling circuit, improving circuit breaker maintenance, sectoring UPS system, electric boards, generator sets, etc.

Source: Aria ACCIDENT ANALYSIS OF INDUSTRIAL AUTOMATION

June 22, 2026

BYPASSING A SAFETY SYSTEM CAUSES A DETONATION

 A leak of over-pressurised and overheated glycol water occurred at a chemical plant after the rupture of a pipe joint. At 2 am, a control room operator recorded a drop in coolant temperature (150°C), preventing vacuum drying operations from continuing. On-call staff diagnosed a loss of communication link between the plant’s utilities automated system and the plant’s process automated system. A specialist in such systems confirmed the defect of a card on the utilities automated system, whose replacement had been postponed until the next morning. Once the specialist left the premises and confident of his diagnosis, the on-call maintenance operator decided to restart the unit. He short-circuited all of the safety mechanisms for hot fluid monitored by the process system, and replicated the corresponding settings in manual mode. Called by another workshop an hour later, the operator abandoned the post for 30 min. Upon his return, the hot fluid had exceeded 180°C, and a noise resembling a detonation shook the plant. After joint rupture, the glycol water vaporised on the premises, which were closed immediately thereafter.

Source: Aria ACCIDENT ANALYSIS OF INDUSTRIAL AUTOMATION