A report in the Hindustan Times about the investigation of a fire in Air India flight on September 4,2009 points out the following:
"A probe by the aviation regulator has found several safety lapses by Air India staff while evacuating 213 passengers from a Mumbai-Riyadh flight after a fire broke out in the aircraft on September 4, 2009. The Directorate General of Civil Aviation (DGCA) concluded that the AI's aircraft maintenance engineer failed to notice a fuel leak from the left side of aircraft before clearing it for take-off. "The engineer had left the bay without giving the final take-off clearance because it was raining," the report said.
Second, the airline ground staff were unable to report the fire to the pilots because the cockpit crew had switched off the radio communication equipment, violating the airline's operation manual. Worse, both the pilots left the aircraft before the evacuation process was complete and not a single cabin crew member was deployed at the end of the inflated emergency slides to assist passengers.
The report also blamed the airline engineers for failing to check the aircraft's fuel channel during routine inspection. "Constant wear and tear caused massive fuel leakage and fire," said the report.
An airport follow-me vehicle informed the air traffic controller on duty about the fuel leak but he wasted significant time in alerting the pilots, the report stated. "As per rules, the controller should have called the aircraft crew by its registration number but it kept calling the flight number," read the report.
The cockpit crew switched off the aircraft engine but was late to start the evacuation process. The cabin crew also overlooked hand signals about the fire from the ground staff."
It always takes a series of human errors to trigger an incident. In the chemical industry also, a similar situation exists. Pressure on production, lack of rest, overloading of equipment, communication gaps and top management disconnects are often common cause reasons for incidents.
Read the news report in this link.
March 16, 2011
March 15, 2011
Chemical Reactor Safety
The UK Health and Safety Executive has a write up on test methods for exothermicity for chemical reactors. Quoting from the article,
“The main types of test are:
1) basic screening tests;
2) isothermal calorimetry, aimed at quantifying reaction kinetics, heats of reaction, etc for particular reaction systems;
3) adiabatic calorimetry, used mainly for examining the runaway potential of reactions and individual compounds; and
4) combination instruments intended not only to give thermal data but also to calculate appropriate reactor vent sizes.
These tests tend not to give absolute results, in that the experimental conditions may affect the data obtained. Factors such as sample size, container material, heating rate, thermal inertia and endothermic effects (eg evaporation, gas evolution and phase changes) can all affect the result. The work, therefore, needs to be carried out by persons who are adequately trained and experienced in this type of investigation, to ensure that in each case suitable techniques are employed and adequate account is taken of experimental variables”.
Read the write up in this link.
Nuclear and process safety - Part 2
For those of who saw the videos of the explosion in the nuclear reactor in Japan, you must have observed the blast wave destroying the wall panels but the metal structure stayed intact. I believe the design worked as intended. But the news that sea water is being used for cooling indicates the seriousness of the situation. In a chemical plant emergency, we do not have to deal with radiation leaks but imagine the plight of the emergency responders in the Japan nuclear plant. They must wear protective clothing for the radiation and tackle the emergency also. For those of you who want to know a little more about the nuclear reactor incident, see this link
Another good article is in this link.
Read an explanation about the second reactor explosion in this link.
Another good article is in this link.
Read an explanation about the second reactor explosion in this link.
March 12, 2011
Earthquakes and nuclear /process safety
Our prayers are with the victims of the Japan earthquake. A BBC news article mentions the following:
"Japan's prime minister has declared a "nuclear emergency" after a number of reactors shut down in the wake of a massive earthquake hitting the country.Eleven reactors at four nuclear power stations automatically shut down, but officials said one reactor's cooling system failed to operate correctly.
Under Japanese law, an emergency must be declared if a cooling system fails.
In total, the country has 55 reactors providing about one-third of the nation's electricity.
In a statement, the Japan Atomic Industrial Forum released a statement that said Prime Minister Naoto Kan had declared the emergency "in case prompt action" had to be taken, but added that "no release of radioactive material" had been detected.
"Since emergency diesel generators at the Fukushima-1 and -2 NPPs are out of order, (energy company) TEPCO sent the emergency report to Nisa. There is no report that radiation was detected out of the site."
The reactor at the Fukushima Daiichi power station that triggered the emergency alert was the 40-year-old Reactor 1, one of six on the site.Reactors 1, 2 and 3 automatically shut down when the Magnitude 8.9 quake shook the plant, while reactors 4, 5 and 6 were not in operation as they were undergoing scheduled inspections.
It is understood that the earthquake cut electricity supplies to the power station, and the back-up generators did not come into operation when the outage occurred. As a result, not all of the cooling systems were available".
Obviously something happened to the back up generators and they could not come in line. We have to wait for the investigation report to come out.
Read the BBC article in this link.
Read an article about the seismic zoning in India in this link.
"Japan's prime minister has declared a "nuclear emergency" after a number of reactors shut down in the wake of a massive earthquake hitting the country.Eleven reactors at four nuclear power stations automatically shut down, but officials said one reactor's cooling system failed to operate correctly.
Under Japanese law, an emergency must be declared if a cooling system fails.
In total, the country has 55 reactors providing about one-third of the nation's electricity.
In a statement, the Japan Atomic Industrial Forum released a statement that said Prime Minister Naoto Kan had declared the emergency "in case prompt action" had to be taken, but added that "no release of radioactive material" had been detected.
"Since emergency diesel generators at the Fukushima-1 and -2 NPPs are out of order, (energy company) TEPCO sent the emergency report to Nisa. There is no report that radiation was detected out of the site."
The reactor at the Fukushima Daiichi power station that triggered the emergency alert was the 40-year-old Reactor 1, one of six on the site.Reactors 1, 2 and 3 automatically shut down when the Magnitude 8.9 quake shook the plant, while reactors 4, 5 and 6 were not in operation as they were undergoing scheduled inspections.
It is understood that the earthquake cut electricity supplies to the power station, and the back-up generators did not come into operation when the outage occurred. As a result, not all of the cooling systems were available".
Obviously something happened to the back up generators and they could not come in line. We have to wait for the investigation report to come out.
Read the BBC article in this link.
Read an article about the seismic zoning in India in this link.
Labels:
Incidents,
Process design
March 11, 2011
Making Process Safety Management Work
I am quoting excerpts from a recent speech by Mr Bob Dudley (Group CEO, BP) that is on the BP website
“We have created a powerful, central safety and operational risk organization headed by Mark Bly, who led our internal investigation of the accident. Mark reports directly to me and sits on our executive team.
His organization has the resources and the mandate to drive safe, reliable, and compliant operations, including intervention rights, in BP’s exploration and production operations anywhere in the world.
The new organization is now in action across BP in four main areas:
First, it is strengthening and clarifying requirements for safe, compliant and reliable operations.
Second, it is deploying around 500 specialist personnel within our businesses to guide, advise, and if necessary, intervene.
Third, it is providing deep technical expertise to our operating businesses.
And fourth, it is intervening where needed to stop operations and bring about corrective actions.
We are already seeing results.
For example, we have shut in one production platform to repair the fire water pumps. Another platform was shut down after the discovery of incorrect specifications for some fasteners. And a producing field was shut down to enable pipeline integrity work to be carried out. Further, we have decided we will not take rigs that do not conform to our standards and there are a number of cases where we have either turned away rigs or are negotiating for modifications which could bring the rig up to our standards.
We are conducting a major review of our risk management systems to ensure we have consistent standards that are applied in a disciplined way across BP.
And in support of all of this, we are linking our performance management and reward system directly to safety and risk management - as well as to key behaviours – teamwork, capability-building, listening and compliance with standards.
We will focus on the critical inputs that drive delivery, namely safety, capability, technology and relationships, rather than focussing primarily on outputs such as production barrels. If we get these right, then the outputs, including dollars, will follow. So we are emphasizing quality over quantity and value over volume.
We also learned a lot about what crisis management means in a world of 24 hour communications with massive social media coverage as well as conventional press and cable broadcasting. I saw how much pressure there is on everyone to take up polarized positions and over-simplify the issues”.
The above points mentioned by the CEO has tremendous significance on Process Safety. I am postulating some simple rules if you want process safety to work:
1. You must be prepared to walk the talk if you want process safety to succeed.
2. Technical expertise is the key to maintaining process safety. Just having standards and a system is not enough. You must have technically competent people who understand the implications of the standards.
3. The board of directors must have direct access to technically competent people who can translate risks and their implications to them.
4.Your organizational framework must institutionalize process safety management
5. If process safety is taken care of, profits will automatically follow. This lesson is most important for the people who control the purse strings!
Read the complete speech in this link.
Labels:
Organisational Culture