A recent news item on February 26th indicates that in the immediate future, Oil Industry Safety Directorate (OISD) is likely to be announced as the single window agency to ensure safety in the oil & gas sector and is also expected to be vested with all necessary statutory powers to fulfill its responsibilities. Several other regulatory changes and announcements that are in the pipeline and expected to be unveiled over the next few months.
What is the future of process safety in India? Do not be surprised if a Chemical Safety Board, similar to the US is set up. Do not be surprised if investigation reports of incidents are put up on the web. But for this to happen, I feel there has to be a strong impetus to the Government to bring in such changes. I am only hoping that another Bhopal is not the impetus!
While on the subject, let us visit the subject of awards and incidents. In my experience, many companies have won many safety awards but then there is a fatal accident. An award for process safety performance cannot be judged by visiting the unit for a few days. It requires commitment day in and day out from top management to really achieve top class process safety performance. I feel that an organization would be better off if it sits back and takes a good look at its performance in process safety periodically.
February 28, 2010
February 26, 2010
Natural Gas Blowing of pipelines causes accident
The CSB has released a statement that mentions that the explosion at the Kleen energy plant in the US occurred during the blowing of new pipelines with natural gas to clear them of debris. There were a number of possible ignition sources.It appears that this is a "common" practice in power plants. I wonder if people are forgetting the basics: flammable gas + air + ignition source = Fire or explosion!
It is very dangerous to assume that ignition sources will not be present!
It is very dangerous to assume that ignition sources will not be present!
February 24, 2010
Monitor your Pressure Safety valves for fugitive emissions
An incident in the US highlights the need to ensure that operational checks are conducted to detect any fugitive emissions from PSV’s. It was reported that about 1.5 tonne of a toxic chemical had leaked from the PSV over a period of two weeks. The leak was finally detected when mass balances did not match. If you have PSV’s discharging to the atmosphere that are mounted on top of vessels tanks and other equipment, ensure that you implement a fugitive emission monitoring program to detect any leak from the safety valve. Many large atmospheric ammonia storage tanks have their PSV’s located on the tank top and any leakage from these valves cannot be detected from the ground level. With more and more habitation coming up near maximum accident hazard units, it becomes imperative that you implement a proactive monitoring PSV leak monitoring program.
Process safety - Do not forget the human being in your design!
Some experts predict that in the future, there will not be any control rooms, but operators and managers individually wearing hi tech equipment like personalized visual displays and control units that will be networked and will be used to control plants. Whatever the future, one thing is sure - the human is going to be around! And continue to commit the same mistakes!! Some examples of design "googlies" are given below:
1. If you install an orifice plate to restrict flow as part of your design, be sure one day it will be removed.
2. If you install an instrument on top of a vessel or equipment and expect the operator to note down the reading, be sure that the reading one day will be noted without the operator going to the top.
3. If you design a tank for full pressure and not for vacuum, when there is a chance of vacuum formation, be sure that the tank will collapse one day due to vacuum.
If you forget to think like an operator, be sure your design will fail one day!!
This also raises another point. In the future is it possible to operate a plant that does not depend on human beings? Ultimately, there will have to be a human being who is looking after that technology and he can also make mistakes!
1. If you install an orifice plate to restrict flow as part of your design, be sure one day it will be removed.
2. If you install an instrument on top of a vessel or equipment and expect the operator to note down the reading, be sure that the reading one day will be noted without the operator going to the top.
3. If you design a tank for full pressure and not for vacuum, when there is a chance of vacuum formation, be sure that the tank will collapse one day due to vacuum.
If you forget to think like an operator, be sure your design will fail one day!!
This also raises another point. In the future is it possible to operate a plant that does not depend on human beings? Ultimately, there will have to be a human being who is looking after that technology and he can also make mistakes!
Labels:
Human factors
February 23, 2010
Advanced instrumentation at Refinery
Please read this article
The Worlds Largest Foundation Fieldbus Project
Reliance Petroleum Limited Needed Foundation Fieldbus to Manage the Most Complex Refinery in the World
Labels:
Instrumentation